First Revised Milestones Submitted: September
18, 2007
Note this is your semester contract, it may be revised if justified, but it is
the basis for your grade.
-
Design Notebook Initial sign-off: September
20, 2007
-
First web page goes live with introductory
page and menu on left. Page must include resumes, individual photos and
milestones: October 11, 2007, 2 pm.
-
Milestone review: November 6th ,
2007
-
Draft Midterm Report: December 6th
, 2007
-
Midterm Report due as a PDF posted as a
completed web page: December 19th, 11:30 am
- Lab Cleanup & Infrastructure Project Completed: Maine Day, April
30th, 2008
- Open House -- Review of Projects, May 1st, 2008, Afternoon
- Final Web Page submitted, for review
during final exam period: Monday May 5th, 2008 Noon,