Milestones for the Controls Group
Milestones for the Linear Actuators Group
Photos
Rules for Competition
Appendix A: Analysis of Tow Cone
Appendix B: Solid Works Drawings for the Tow Cone
Mid-Term Report for the Controls Group
Mid-Term Report for the Linear Actuators
Details on how to become Scuba Certified
Final Report
Poster for Controls
Poster for Linear Actuators
Lab for Linear Actuators
Lab for Controls Group
|
- September 18, 2007 Initial Milestones (Completed)
- September 21, 2007 All appointments for Scuba Certification Due (Completed)
- September 25, 2007 Rules for the Competition (Completed)
- October 4, 2007 : Learn basic stamp programming (Completed)
- October 6,2007 : Check existing control system (Completed)
- October 10, 2007: First web page goes live with introductory page and menu on left. Page must
include resumes, individual photos and milestones. (Completed)
- October 15, 2007: Design joystick circuitry ( Completed)
- October 17, 2007: First version of programming for the joystick(Completed)
- October All forms for competition filled out and sent in (can't complete until a later date)
- October 24, 2007 : Design and Build tow cone (Completed)
- November 7, 2007: Milestone review(Completed)
- November 12, 2007: Create joystick/Basic STAMP chip (Completed)
- November 12, 2007: Modify the existing manual
controls to eliminate rough edges and create a more ergonomical design (Completed)
- November 21, 2007: Adjust the position of the manual controls to allow for easier access (Completed)
- November 27, 2007: Compare Design concepts for the joystick design concept to put into production ( Completed)
- November 29, 2007: Begin installation of the bow planes (Completed)
- December 4, 2007: Attach serial port to circuit board (Completed)
- December 4, 2007: Create housing for circuit boards (Completed)
- December 6, 2007: Combine Basic STAMP chip with serial chip (Completed)
- December 5, 2007: Draft Midterm Report (Completed)
- December 6, 2007: Order the 400 Series Buccaneer Environmentally Sealed Connectors(Completed)
- December 11, 2007: Joystick Fabrication and first water test of the joystick due (Completed)
- December 13, 2007: Integrated fly-by-wire (Completed)
- December 19, 2007: Final midterm report (Completed)
Spring Term Milestones:
- January 31, 2008: $200 registration fee due for the completion (Completed)
- March 12, 2008: Online portion of scuba training finished (Completed)
- March 18, 2008: Begin in water training for scuba certification (Completed)
- March 20, 2008: Review safety requirements and make necessary changes (Completed)
- April 6, 2008: Open water dive and final scuba certification (Completed)
- April
2008: Test results from the
stabilization of the sub, modified safety devices, servos in
the water, bow planes and adjustments to their angle (Completed)
- April 14, 2008 : Installation into sub complete and any finishing touches (Completed)
- Maine Day, April 30, 2008: Lab Cleanup (Completed)
- May 2008: Final Report and Poster (Completed)
- May 2008: Prepare an Oral Design Presentation that meets competition requirements (Completed)
- May 2008: Paint the inside of the sub (Completed)
- May 1, 2008: Open House -- Review of Projects (Completed)
|