Milestones
Team: Eric M
Martin, Richard Peale, Jacob Folz, Patrick Bates
All Completed Task Dates Highlighted in Green
Fall Semester
- Develop Design Issues for Tidal Turbine. October 4, 2007
- Determine Range
of Power and speed for
propeller. October 11, 2007
- First Web page goes live with introductory page
and menu on left.
-Page must include
resumes, individual photos and milestones. October 11, 2007
- Design specifications for modifications to test
propeller/turbine power output. October
18, 2007
- Design
guard modifications on drive system on tow tank. October 18, 2007
- Instrumentation selection and schematic for
carriage. October 23, 2007
- Create drawings of dynamometer for test use. October 30, 2007
- Create drawings of mounting system of propeller
for carriage. November 6, 2007
- Milestone Review. November 6, 2007
- Purchase order requests submitted for
instrumentation for dynamometer. November 13, 2007
- Purchase order for complete drive resistance
unit parts. November 20, 2007
- Draft Midterm Report. December 6, 2007
- Complete fabrication of modifications to
carriage. December 13, 2007
- Midterm report due as a PDF posted as a
completed web page. December 21, 2007
Spring Semester
- Design procedure completed for experiment to
produce propeller/turbine power output curves. January
29, 2008
- Install
modifications to carriage on Tow –Tank February 12, 2007
- Mount propeller on carriage for test pull. March
18, 2007
- Completed data acquisition software for
obtaining experimental data demo. February 26, 2007
- First test data from propeller in water. March
18, 2007
- Re-Design experiment procedure and parts as
needed. April 1, 2007
- Run experiment to determine power producing
propeller curves from set velocities of flow.
April 8, 2007
- Post-processing of data to develop power
curve. April 22, 2007
- Team Project Poster. April
29, 2007
- Lab Cleanup & Infrastructure project
completed. April 30, 2008
- Open House – Review of Projects. May 1,
2008
- Final Web page submitted, for review during
final exam period. Monday May 5th, 2008. 12:00 pm
|