1. Project Team
Selection Complete: September 1, 2011 2. First Revised
Milestones Submitted: September 8, 2011 4. System Schematic:
October 2nd, 2011 5. First web page
goes live with introductory page and menu on
left. Page must include resumes,
individual photos and milestones:
October 4, 2011, 4
pm. 6. Milestone review:
October 25, 2011 7. Draft Midterm
Report: November 30th , 2011 8. Midterm Report due
as a PDF posted as a completed web page:
December 8th, 5 pm 9. Order Final PCM: 1/18/2012 18.
Lab Cleanup &
Infrastructure Project Completed: Maine Day,
April 25, 2012 19.
Open House -- Review of
Projects, April 26, 2012, Afternoon
3. Initial model outline for the system: September 25, 2011
10. Frame Fabrication: 1/27/2012
11. Thermal Conductivity Experiment: 2/5/2012
12. Ultrasonic Testing: 3/10/2012
13. Experimental 1/3 Scale Panel Testing: 3/30/2012
14. Heat Exchanger Fabrication: 4/6/2012
15. Unit Assembly : 4/10/2012
16. Control System: 4/14/2012
17. Final Testing: 4/18/2012
20. Final Web Page submitted: 5/1/2012