Second Semester Milestones
ECT Date Complete Milestone
1/24/06 1/23/06
  • Set new milestones for second semester
2/7/06 2/14/06
  • Order Pulley and Idler
2/7/06 2/7/06
  • Order Wire Rope
2/7/06 2/14/06
  • Order hub (key hole)
2/23/06 2/28/06
  • Begin Machining Parts
2/9/06 2/7/06
  • Meet with Doug Reed about dynamometer
2/28/06 2/28/06
  • Drawings of guard and pulley support
2/28/06 2/28/06
  • Choose material for drive belt guard
3/2/06 2/14/06
  • Begin Research Dynamometer
3/21/06 3/21/06
  • Assembly of Tow Tank Drive Belt
3/21/06 3/21/06
  • Design of Guard Supports
3/23/06 3/23/06
  • Construction of Guard Supports
3/27/06 3/27/06
  • Open House, Final Presentation Due
5/3/06 5/3/06
  • Infrastructure Project
5/5/06 5/5/06
  • Begin Testing of tow Tank Drive Belt
5/11/06 5/11/06
  • Final report due along with final web page turned in
5/11/06 5/11/06
  • Turn in Design Notebook




ECT Date Completed                                           Milestones
9/15/05 9/15/05
  • Proposal for modified milestones and initial deliverables
10/4/05 10/4/05
  • First web page completed
10/4/05 10/4/05
  • Evaluation on current belt drive system
10/20/05 10/20/05
  • Sketches of current belt finished and reviewed by user
10/20/05 10/20/05
  • Report on current drive belt system
10/25/05 10/25/05
  • Proposal for new design of drive system including computer models
10/26/05 10/26/05
  • Quotations for materials and part costs
11/17/05 11/17/05
  • Updated web page
11/21/05 11/21/05
  • Design of the pulley and idler for the prototype
12/6/05 12/13/05
  • Presentation of first semester results
12/6/05 11/10/05
  • Water Demonstration of operational machine


[   UMaine  | Milestones   Links  |   Photos |   Design Considerations  |  Drive Belts |   Sr Design ]

{Final Report}