Milestones (revised 9-17-06)
-
Check fluids and run sled: September 8th,
2006
-
Ensure gas is available and exhaust emissions
tester is operational: September 15th, 2006
-
Resolved problem with battery power in sled:
September 15th, 2006
-
Demonstrate ability to cool sled on dyno:
September 15th, 2006
-
Dyno test sled with piggyback, verify
integrity of engine, dyno results plotted: September 21th, 2006
-
If a
cooling problem exists provide diagnostic tree associated with source of
problem, tree should include, exhaust back pressure, cooling system flow rate,
water temperature sensors and appropriate use of exhaust gas temperature
sensors.: September 26, 2006
-
Order demo board Mega Squirt II after
verification of ability to control sled, sign off from Yamaha team required:
September 26th, 2006
-
First web page goes live with introductory
page and menu on left. Page must include resumes, individual photos and
milestones: October 12, 2006, 2 pm.
-
Dummy test board set up with Mega Squirt and
ability to replicate Yamaha and Arctic Cat engines October 17, 2006
-
Demonstrate the ability to change the program
on FM unit: October 24, 2006
-
Wiring redesigned and installed on Arctic cat
that allows Mega Squirt to be disconnected using industry or race quality
connectors and moved between demo board and snowmobile. Wiring should be
fail safe and unable to be connected in a manner that will result in damage to
unit or sensors: November 7, 2006
-
Milestone review: November 7th ,
2006
-
ECU installed in Arctic Cat with prototype
brackets and complete drawing package race ready bracket designs:
November 14, 2006
-
ECU
installed and operating engine on dyno, needs not run well!: November 21 ,
2006
-
Retest snowmobile on dyno for emissions and
fine tune performance. Program at least four curves that show the effect of
piggyback on emissions: November 28 , 2006
-
Draft Midterm Report: December 5th
, 2006
-
Order second ECU for programming back up: December 7, 2006
-
Connectors installed to make ECU changeover
possible and demonstrate a less than 10 minute ECU change: January 26th , 2007
-
Attend and present snowmobile at least two
events, (for example Caribou Winter Carnival/Snowmobile Festival was Feb.
16-26 in 2006 and the International Snowmobile Festival was February 3-5 in
2006). Demo must include exhaust emissions analyzer and drive by test with
sound level meter with a fully operational snowmobile. (March 1st ,
2006)
- Lab Cleanup: Maine Day, May 2nd , 2007
- Open House -- Review of Projects, May 3rd , 2007
|
| Draft Milestones: Revised milestones, 9-12-06 -- not approved
-
Check fluids and run sled: September 8th,
2006
-
Ensure gas is available and exhaust emissions
tester is operational: September 15th, 2006
-
Resolved problem with battery power in sled:
September 15th, 2006
-
Dyno sled for comparison: September 15th,
2006
-
Emission test: September 15th, 2006
-
test old piggy back system: September 15th,
2006
-
Verify integrity of engine: September 18th,
2006
-
Determine whether to use piggy back, or
upgrade to the Mega Squirt: September 20th, 2006
-
Research mega squirt system: September 20th,
2006
-
Determine cost and order system: September 25th,
2006
-
First web page goes live with introductory
page and menu on left. Page must include resumes, individual photos and
milestones: October 12, 2006, 2 pm.
-
Consolidate wiring: October 13th,
2006
-
Submit complete drawing package for piggyback
enclosure with dimensions, materials and parts list: October 19th ,
2006
-
install system for FM: November 1st,
2006
-
initial programming of system: November 7th
, 2006
-
Milestone review: November 7th ,
2006
-
test the new system: November 7th , 2006
-
Demonstrate the ability to change the program
on FM unit: November 14th , 2006
-
Retest snowmobile on dyno for emissions and
fine tune performance. Program at least four curves that show the effect of
piggyback on emissions: November 17th , 2006
-
If cooling problem still exists, determine
source of problem and remedy
determine optimal catalytic converter based on size, weight, air flow, and
emissions control performance: November 17th, 2006
-
Draft Midterm Report: December 5th
, 2006
-
Second FM unit up and programmable: January 26th , 2007
-
Attend and present snowmobile at least two
events, (for example Caribou Winter Carnival/Snowmobile Festival was Feb.
16-26 in 2006 and the International Snowmobile Festival was February 3-5 in
2006). Demo must include exhaust emissions analyzer and drive by test with
sound level meter with a fully operational snowmobile. (March 1st ,
2006)
-
Lab Cleanup: Maine Day, May 2nd , 2007
- Open House -- Review of Projects, May 3rd , 2007
Initial Draft Milestones
- Proposal for modified milestones and initial deliverables: September 15,
2006
- Ensure gas is available and exhaust emissions tester is operational:
September 19, 2006
- Verify integrity of engine, test with water and coolant problems resolved:
September 26, 2006
- Exhaust gas test of existing system complete: October 3, 2006
- First web page goes live with introductory page and menu on left.
Page must include resumes, individual photos and milestones: October 12, 2006,
2 pm.
- Submit complete drawing package for piggyback enclosure with dimensions,
materials and parts list: October 19, 2006
- Demonstrate the ability to change the program on existing piggyback unit:
October 21, 2006
- Milestone review: November 7, 2006
- Second Piggyback unit up and programmable: November 21, 2006
- Optimization of emissions using piggyback, program at least four curves
that show the effect of piggyback on emissions: November 28, 2006.
- Draft Midterm Report: December 5, 2006
- Attend and present snowmobile at at least two events, (for example Caribou
Winter Carnival/Snowmobile Festival was Feb. 16-26 in 2006 and the
International Snowmobile Festival was February 3-5 in 2006). Demo must
include exhaust emissions analyzer and drive by test with sound level meter
with a fully operational snowmobile. (March 1, 2006)
- Lab Cleanup: Maine Day, May 2, 2007
- Open House -- Review of Projects, May 3, 2007
|