Advanced Exhaust Air Energy Heat Pump
- Proposal for modified
milestones and initial deliverables: September 14, 2006
- Description of ventilation air loads October 3, 2006
- First web page goes live with introductory page and menu
on left. Page must include resumes, individual photos and milestones: October
10, 2006, 5 pm.
- Ventilation air load variation over a design day in July
& Jan:: October 17, 2006
- Heat pump operating states, initial definitions:
refrigerant properties and mass flow rates required, P-h diagrams October 31,
2006
- Milestone review: November 6, 2006
- Initial projection of energy delivered to/removed from
incoming ventilation air: November 20, 2006.
- Draft Midterm Report: December 5, 2006
- Final midterm report complete with test results from
servo system: December 19, 2006
Second Semester
- Complete Green Loan Application/Compile coil sizing information for pricing: January 25, 2007
- Complete presentation for Green Loan Fund Board: February 1, 2007
- Complete rough outline of final report: February 27, 2007
- Compile Parts list/Complete design schematic of system: April 3, 2007
- Appropriately size pipes & choose expansion valve/Equipment selection & pricing complete: April 12, 2007
- Complete project poster for Hosmer Lab dedication: April 13, 2007
- Final Report : May 7, 2007