Milestones
Blue-Completed
- Identify primary contact person/s at COA and MDR: September 18, 2007
- First Web page draft: September 18, 2007
- Completed interviews and summary document to determine power needs
for the research station: September 25, 2007
- Review available Literature and Publications on Maine offshore wind
energy availability
- Generate a power density estimation for wind on Mount Desert Rock
-
First web page goes live with introductory
page and menu on left. Page must include resumes, individual photos and
milestones: October 11, 2007, 2 pm.
-
Complete evaluation of average wind speed
-
Complete estimation of cost per kilowatt hour
generated
-
Summery of available literature on
optimization of wind generation
- Complete summary website of design considerations
- Grounding
- Installation
- Cost / Capacity
- Survivability
- Maintenance
- Milestone review: November 6th , 2007
- Identify hardware capable of powering the rock, generation
capability
- Draft Midterm Report: December 6th , 2007
- Complte order information for nessacry equipment and apparatus
- Turbine, Tower, Desalination unit
- Midterm Report due as a PDF posted as a completed web page: December
19th, 11:30 am
- Complete identification of control hardware requirements
- Completed total budget
- Lab Cleanup & Infrastructure Project Completed: Maine Day, April
30th, 2008
- Open House -- Review of Projects, May 1st, 2008, Afternoon
- Final Web Page submitted, for review during final exam period:
Monday May 5th, 2008 Noon
|