Milestones
Blue-Completed
  • Identify primary contact person/s at COA and MDR: September 18, 2007
  • First Web page draft: September 18, 2007
  • Completed interviews and summary document to determine power needs for the research station: September 25, 2007
  • Review available Literature and Publications on Maine offshore wind energy availability
  • Generate a power density estimation for wind on Mount Desert Rock
  • First web page goes live with introductory page and menu on left. Page must include resumes, individual photos and milestones: October 11, 2007, 2 pm.
  • Complete evaluation of average wind speed 
  • Complete estimation of cost per kilowatt hour generated
  • Summery of available literature on optimization of wind generation
  • Complete summary website of design considerations
    • Grounding
    • Installation
    • Cost / Capacity
    • Survivability
    • Maintenance
  • Milestone review: November 6th , 2007
  • Identify hardware capable of powering the rock, generation capability
  • Draft Midterm Report: December 6th , 2007
  • Complte order information for nessacry equipment and apparatus
    • Turbine, Tower, Desalination unit
  • Midterm Report due as a PDF posted as a completed web page: December 19th, 11:30 am
  • Complete identification of control hardware requirements
  • Completed total budget
  • Lab Cleanup & Infrastructure Project Completed: Maine Day, April 30th, 2008
  • Open House -- Review of Projects, May 1st, 2008, Afternoon
  • Final Web Page submitted, for review during final exam period: Monday May 5th, 2008 Noon