Project Timeline
Fall 2008
Establish rough initial milestones
Research pricing and schedule SCUBA instruction
Introductory webpage up and running
Fully functional webpage online
New hull design completed
SCUBA certification completed
Rough plug completed
Plug finished and ready for fiberglass
September 16, 2008 - Completed
September 30, 2008 - Completed
October 7, 2008 - Completed
October 28, 2008 - Completed
November 7, 2008 - Completed
November 11, 2008 - Completed
November 25, 2008 - Completed
December 12, 2008 - Completed
Spring 2009
Apply first layer of light fiberglass
Apply heavy fiberglass to drive section and foam elsewhere
Integrate drive system component mounts
Apply finish fiberglass to entire submarine
Cut access hatch and remove plug material
Integrate window into submarine
Apply and sand body filler until ready for paint
Complete final clear coat of hull finish
January 27, 2009 - Completed
February 3, 2009 - Completed
February 10, 2009 - Completed
February 24, 2009 - Completed
March 24, 2009 - Completed
April 7, 2009
April 10, 2009
April 21, 2009