Facilities Alerts & Work Zones.
Dig This!
Request Services
Utility Costs
Reporting Problems.
Frequently Asked Questions.
Overview of Campus Infrastructure.
Capital Construction Projects & Services.
Resources for Designers & Contractors.
Meet Facilities.
FM Home Page

Special Services.

Motor Pool.
UMAine Recycles!
Campus Map.
Insurance.
Storm Water Management.

Department of Facilities Management

Facilities Overview of Campus
 

updated 2/22/08

UNIVERSITY OF MAINE - OVERVIEW

Total Number of University Owned Buildings all locations 345
Total University Building Area
(gross square feet, excludes leased space)
 4,483,466
Total Building Value for University Assets $833,317,037
Average Age of Main Campus Buildings (includes new additions) 39.5 years
Total Contents Value for University Assets $243,313,394
   
Main Campus Stats  
Total Number of Buildings 211
Total Area (gross square feet) 3,996,988
Total Building Value $766,258,457
   
Main Campus Building Contents Valuation
Total Campus $233,915,876
Total E&G $208,173,669
Total Auxiliary $25,742,207
   
Main Campus - E&G Buildings  
Total Number of Buildings 148
Total Area (gross square feet) 3,088,530 (70% of total)
Total Building Value $497,200,597 (65% of total)
   
Main Campus - Auxiliary Buildings  
Total Number of Buildings 63
Total Area (gross square feet) 1,331,998 (30% of total)
Total Building Value $269,057,860 (35% of total)
   
Acreages  
Contiguous UMaine Campus
  (includes Main Campus, Witter Farm, Demeritt Forest, University Park)
1,690
Main Campus 443
University Farms
  (includes Witter Farm)
1,340
Research Facilities 194
University Forests
  (includes Demeritt Forest)
5,125
   
Infrastructure Summary and Replacement Values  
Paved Surface: 3,592,248 s.f. $7,184,496
Water Lines: 36,379 feet $3,706,900
Fire Hydrants: 51 $76,500
Sanitary Sewer: 47,995 feet $4,876,300
Sanitary Manholes: 217 $434,000
Storm Sewer: 63,110 feet $6,311,000
Storm Manholes: 721 $1,442,000
Electric Lines: 55,351 feet $4,151,325
Electric Pits: 66 $132,000
Telcom Lines: 185,418 feet $18,541,800
Telcom Pits: 49 $1,225,000
Steam Lines: 28,776 feet $23,020,800
Steam Pits: 105 $5,250,000
Outdoor Lighting: 473 poles, 761
  Lamps, 439,680 feet wire
$4,637,388
Landscape: 627 acres $34,485,000
Exterior Accessibility Features: $1,750,000
Signage: $100,000
Exterior Campus Accessories:
  (benches, trash receptacles, picnic tables, etc.)
$50,000
Total: $117,374,509


 
 




Aerial View of Campus


TelCom Pits


Earthwork