updated 2/22/08
UNIVERSITY OF MAINE - OVERVIEW
| Total Number of University
Owned Buildings all locations |
345 |
Total University Building
Area
(gross square feet, excludes leased space) |
4,483,466 |
| Total Building Value for
University Assets |
$833,317,037 |
| Average Age of Main Campus
Buildings (includes new additions) |
39.5 years |
| Total Contents Value for
University Assets |
$243,313,394 |
| |
|
| Main Campus Stats |
|
| Total Number of Buildings |
211 |
| Total Area (gross square feet) |
3,996,988 |
| Total Building Value |
$766,258,457 |
| |
|
| Main Campus
Building Contents Valuation |
| Total Campus |
$233,915,876 |
| Total E&G |
$208,173,669 |
| Total Auxiliary |
$25,742,207 |
| |
|
| Main Campus - E&G Buildings |
|
| Total Number of Buildings |
148 |
| Total Area (gross
square feet) |
3,088,530 (70% of total) |
| Total Building
Value |
$497,200,597 (65% of total) |
| |
|
| Main Campus - Auxiliary
Buildings |
|
| Total Number of Buildings |
63 |
| Total Area (gross
square feet) |
1,331,998 (30% of total) |
| Total Building
Value |
$269,057,860 (35% of total) |
| |
|
| Acreages |
|
Contiguous UMaine Campus
(includes Main Campus, Witter Farm, Demeritt Forest, University Park) |
1,690 |
| Main Campus |
443 |
University Farms
(includes Witter Farm) |
1,340 |
| Research Facilities |
194 |
University Forests
(includes Demeritt Forest) |
5,125 |
| |
|
| Infrastructure Summary and Replacement
Values |
|
| Paved Surface: 3,592,248 s.f. |
$7,184,496 |
| Water Lines: 36,379 feet |
$3,706,900 |
| Fire Hydrants: 51 |
$76,500 |
| Sanitary Sewer: 47,995 feet |
$4,876,300 |
| Sanitary Manholes: 217 |
$434,000 |
| Storm Sewer: 63,110 feet |
$6,311,000 |
| Storm Manholes: 721 |
$1,442,000 |
| Electric Lines: 55,351 feet |
$4,151,325 |
| Electric Pits: 66 |
$132,000 |
| Telcom Lines: 185,418 feet |
$18,541,800 |
| Telcom Pits: 49 |
$1,225,000 |
| Steam Lines: 28,776 feet |
$23,020,800 |
| Steam Pits: 105 |
$5,250,000 |
Outdoor Lighting: 473 poles, 761
Lamps, 439,680 feet wire |
$4,637,388 |
| Landscape: 627 acres |
$34,485,000 |
| Exterior Accessibility Features: |
$1,750,000 |
| Signage: |
$100,000 |
Exterior Campus Accessories:
(benches, trash receptacles, picnic tables, etc.) |
$50,000 |
| Total: |
$117,374,509 |
|
 |

Aerial View of Campus

TelCom Pits

Earthwork
|